CLIENT:
RDRML
Contract Period:
January 2024 - Ongoing
CONTRACT VALUE:
3.8M
RDR Syphon Repair - North Ashburton River
The Rangitata Diversion Race (RDR) was in need of repairs after the June 2021 Floods. The flood waters got in behind the original concrete protection work from 1938 and damaged seven syphons, tearing off some of the concrete armouring. We were the chosen contractor to undertake the repairs, currently making great progress on the 4th Syphon. Our great team of concrete placers working hard to get each individual panels boxed & poured correctly as well as placing a few pre poured, pre-cast panels for the straighter section of the syphon design. Check out our gallery below to see the progress.
RDR Syphon Repair - South Ashburton River
The South Ashburton River Syphon Repairs were our first on the list to complete. Both are now fully complete, on time and on budget. The images below show case the handy work from our Team.