CLIENT:


Ashburton District Council

Contract Period:


October 2025 - November 2025

CONTRACT VALUE:


$400K

 Ashburton Closed Landfill Slope Remediation


Grant Hood Contracting Ltd successfully delivered a comprehensive package of works for the Ashburton Closed Landfill Slope Remediation project, providing a stable and environmentally resilient solution for this important community site.


Scope of Works

Our team undertook a full programme of earthworks, environmental controls, and finishing activities, including:

  • Final slope clearing to prepare landfill faces for remediation
  • Rehandling and placement of stockpiled materials to reshape and stabilise the slope
  • Import and placement of engineered fill to meet specified levels and ensure long-term structural integrity
  • Installation of geotextile systems to enhance slope stability and reduce erosion risk
  • Precision slope profiling to achieve final design contours
  • Landscaping and hydroseeding to establish durable vegetation and support long-term environmental performance


Project Outcomes

These works were completed to meet the project’s final design specifications, provide enduring slope stability, and deliver a high-quality, sustainable outcome for the Ashburton community.


Ongoing Contract Works

Grant Hood Contracting Ltd will continue to support this site under a long-term maintenance and development contract for the next five years, with this project forming part of an ongoing programme of works.