CLIENT:
Allenton School
Contract Period:
March - June 2024
CONTRACT VALUE:
-
Allenton School
This job involved completing the site works for the New Sports Courts at Allenton School.
Scope
- Design of the courts including site investigation, survey, set out and levels to connect to existing hardstand and landscaping.
- Design and identification of the trafficable area suitable for heavy vehicles driving over and turning (e.g. Fire engines, Life Education van and prime mover)
- Investigate the location of all buried services. Existing stormwater services (hall stormwater and existing surface drainage) are to be retained and or modified to suit the new site layout.
- Other services in the area are to be reported if found to be live and decommissioned or removed outside the footprint. NB: Existing cabling, water and sewer pipes servicing the former CEBUS block are anticipated and now redundant
- Drainage design including surface falls, catchment channels or grates to connect to existing stormwater system and / or new drainage soakpit.